Multiple Choice
Which of the following rules maximizes the number of tasks that can be completed by a system in a given period of time?
A) as soon as possible
B) as late as possible
C) shortest task duration first
D) minimum slack first
E) most critical successor
Correct Answer:

Verified
Correct Answer:
Verified
Q56: All tasks can be crashed to some
Q57: Often it is beneficial to crash activities
Q58: Explain how the commonly made assumption of
Q59: For resources that are consumed when used,
Q60: Briefly overview Goldratt's common chain of events.
Q62: Microsoft Project allows the project manager to
Q63: The shortest-task-first priority rule for assigning resources
Q64: Applying "line balancing" techniques to balance the
Q65: A task's duration is a function of
Q66: If resources were not scarce, the resource