menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Computing
  3. Study Set
    Using MIS Study Set 4
  4. Exam
    Exam 11: Managing Development
  5. Question
    Any Task Not on the Critical Path Can Run Late
Solved

Any Task Not on the Critical Path Can Run Late

Question 87

Question 87

True/False

Any task not on the critical path can run late without ever delaying the project.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q82: The systems development life cycle (SDLC)process begins

Q83: The development team will create a data

Q84: Does the company have a management policy

Q85: The average contribution per worker is directly

Q86: Each task in a project should culminate

Q88: With plunge installation,the organization shuts off the

Q89: A function point is the sequence of

Q90: Explain the importance of configuration control.

Q91: System conversion refers to the process of

Q92: What are the tools used to meet

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines