Multiple Choice
Project teams create a(n) ________,which is a hierarchy of the tasks required to complete a project,to reduce the confusion of complex interrelated tasks.
A) enterprise task sheet
B) work-breakdown structure
C) Gantt chart
D) scope statement
Correct Answer:

Verified
Correct Answer:
Verified