Multiple Choice
Corrie contractually agreed to build a house for Ed in exchange for $250 000.After completing about 75 percent of the project,Corrie ran out of resources and informed Ed that she could not continue.She therefore abandoned the job,as well as a substantial amount of materials at the work site.After Corrie left,Ed used the abandoned materials to finish the job himself.Which of the following statements most likely is TRUE?
A) Corrie is entitled to partial payment on the basis of the doctrine of substantial performance.
B) Although she is not entitled to be paid for her services,Corrie is entitled to sue on the contract in order to be paid for the materials that Ed used to complete the project.
C) Because Ed completed the job,Corrie is entitled to have the contract discharged on the basis of performance.
D) If the court classifies the parties' agreement as an entire contract,then Ed is liable for the materials that he used in completing the project,but he is not liable for the work that Corrie performed.
E) Because Corrie did not complete the project,the parties never actually had a contract.
Correct Answer:

Verified
Correct Answer:
Verified
Q20: Madeleine entered into a contract with Blue
Q21: Miguel filled his shopping cart with groceries
Q22: Depp Designs Inc is a landscaping company.Roger
Q23: Which of the following statements is TRUE?<br>A)The
Q24: Brock contractually agreed to build a deck
Q27: Tippi and Alfred entered into a contract
Q28: Boris purchased confidential information from Natasha for
Q29: Which of the following techniques for discharging
Q39: The difference between a condition precedent and
Q56: Explain the difference between a "condition," a