Essay
On March 1,Shoshanah agreed to manufacture and sell a widget to Marshall for a total price of $50 000.He paid $20 000 immediately and promised to pay the remainder on June 15.The contract required Shoshanah to deliver the widget to Marshall on June 1.On April 15,Marshall spent $10 000 altering his production plant in a way that would accommodate the widget that he expected to receive from Shoshanah.On May 20,Shoshanah informed Marshall that she would not be able to deliver as promised.On June 1,the market value of a widget was $65 000.Marshall can acquire a similar widget for that amount,but he will have to once again spend $10 000 in renovations to his production plant to accommodate that substitute.(No two widgets are exactly alike and each one has unique requirements. )??Is Marshall entitled to receive expectation damages? If so,on what basis and in what amount? Is Marshall entitled to receive reliance damages? If so,on what basis and in what amount? Is Marshall entitled to receive restitution? If so,on what basis and in what amount? If Marshall has an option between several types of damages,which one should he choose?
Correct Answer:

Verified
Marshall can claim expectation damages u...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q4: If defendants in a private law case
Q17: On March 26, Sanjeev agreed to sell
Q61: Silvio agreed to perform as a pianist
Q62: Restitution is<br>A)a cause of action that sometimes
Q62: Why are the courts willing to award
Q64: Joshua contractually agreed to sell a widget
Q68: "Reliance damages cannot be used to escape
Q69: When will punitive damages be available for
Q69: If the plaintiff proves an enrichment,a corresponding
Q70: Woody entered into a contract with Jezebel.She