Multiple Choice
If a net present value analysis for a normal project gives an NPV greater than zero, an internal rate of return calculation on the same project would yield an internal rate of return the required rate of return for the firm.
A) greater than
B) less than
C) equal to
D) cannot be determined from the information given
Correct Answer:

Verified
Correct Answer:
Verified