Question 27

Multiple Choice

Builders,Inc.,agrees to construct an office building for Champion Fitness Clubs,Inc. The project proceeds according to plan,but before it is done,Champion tells Buildersto quit. Buildersmay recover


A) the contract price less costs of materials and labor.
B) the contract price.
C) the costs needed to complete construction.
D) profits plus the costs incurred up to the time of the breach.

Correct Answer: