Multiple Choice
Balancing a production line includes the following tasks,EXCEPT:
A) Finding a cycle time in which each workstation can complete its tasks
B) Take into account precedence relationships among tasks
C) Identify the task with the longest operation time
D) Calculate the number of workstations that completes the job in the minimum amount of time