Question 17

Multiple Choice

Cooper's Brakes,Inc.,enters into a contract with Byron's Service to fix Cooper's hydraulic equipment.Byron delays the repair for three days,but is not aware that Cooper loses a certain percentage of profit each day the equipment is out of service.Cooper is most likely to be awarded


A) compensatory damages.
B) nominal damages.
C) punitive damages.
D) no damages.