In the context of operational plans, which of the following is a difference between single-use plans and standing plans?


A) Single-use plans cover unique, one-time-only events, whereas standing plans handle frequently recurring events.
B) Single-use plans use quantitative planning, whereas standing plans use qualitative planning.
C) Single-use plans include policies and procedures, whereas standing plans include rules and regulations.
D) Single-use plans are operational plans, whereas standing plans are tactical plans.

Correct Answer: