Multiple Choice
For a project manager, monitoring _____.
A) requires guiding, supervising, and coordinating the project team's workload
B) involves controlling capital
C) consists of staffing, which includes selecting the project team and assigning specific tasks to team members
D) includes identifying and arranging project tasks and estimating completion times and costs
Correct Answer:

Verified
Correct Answer:
Verified