Multiple Choice
MATCHING
Identify the letter of the choice that best matches the phrase or definition.
a.project management
f.weight
b.project coordinator
g.bottom-up technique
c.project leader
h.dependent
d.milestone
i.concurrent
e.constraint
j.predecessor
-In discussing PERT/CPM charts, you discuss the types of task patterns that can occur in a project schedule. You give an example of two tasks, A and B, that can both begin as soon as task C is finished. Which of the following is NOT a true statement about tasks A and B?
A) They are predecessor tasks of each other.
B) They are concurrent tasks.
C) They each depend on task C.
D) They are multiple successor tasks of task C.
Correct Answer:

Verified
Correct Answer:
Verified
Q53: In most systems analysis tasks,time and people
Q76: In addition to tasks, every project has
Q77: Using a WBS allows you to manage
Q78: MATCHING<br>Identify the letter of the choice that
Q79: A _ cannot be started until one
Q82: In GanttProject, unlike in Microsoft Project, you
Q83: A risk _ plan is a proactive
Q84: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5608/.jpg" alt=" -A(n) _ is
Q85: Microsoft claims that Microsoft Project has the
Q86: A PERT/CPM chart does not show the