Multiple Choice
-At the end of the systems implementation phase, the final report to management should include ____.
A) final versions of all system documentation
B) a comparison of actual costs and schedules to the original estimates
C) planned modifications and enhancements to the system that have been identified
D) all of the above
Correct Answer:

Verified