    The Critical Path in a PERT Network Is Important to Know
Solved

The Critical Path in a PERT Network Is Important to Know

Question 29

Question 29

Multiple Choice

The critical path in a PERT network is important to know because it determines the ____________ needed to complete a project.


A) length of time
B) amount of money
C) number of employees
D) number of activities

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q9: Facilities are the physical resources used in

Q24: The time required to complete the time-based

Q25: _ certifies people as quality professionals.<br>A)ISO<br>B)ASQ<br>C)ANSI<br>D)SAI

Q27: JIT and TQM are part of _

Q28: What is the only real way to

Q30: Juanita has setup a new bakery that

Q31: A statistical test that aids in determining

Q32: _ is/are a network scheduling technique that

Q33: Michaela would like to arrange her new

Q34: Which of the following is not one

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines