Multiple Choice
Identify the statement that is NOT a major disadvantage of placing a project within a functional element of the parent organization.
A) There is a tendency to suboptimize the project.
B) The client is not the primary focus of activity in the function.
C) The motivation of people assigned to the project tends to be weak.
D) The functional division contains the normal path of advancement for individuals whose expertise is in the functional area.