Multiple Choice
Identify the statement that is NOT a major advantage of placing a project in the matrix approach.
A) A single individual, the project manager, takes responsibility for managing the project.
B) The project will have access to representatives from the administrative units of the parent firm.
C) The division of authority between the project manager and the functional managers is complex.
D) There is less anxiety among team members about what will happen to them when the project is completed.
Correct Answer: