Multiple Choice
The use of PERT (ADM) has declined sharply in recent years because a large majority of project management software __________.
A) have become obsolete
B) use probabilistic techniques
C) generate CPM networks
D) are characterized by high prices
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q10: The difference between the late start and
Q27: Task F has duration of 10 days
Q36: The authors, when discussing networks, describe a(n)_
Q38: _ law suggests that work expands to
Q40: A(n)_ is a specific task or set
Q42: The series of connected activities (or intermediate
Q44: In AOA networks, an activity of zero
Q45: A precedent relationship where the completion of
Q46: Using precedence diagramming methods, activity B must
Q53: The calculation of the standard deviation for