Multiple Choice
__________ have a weakness of being difficult to follow when multiple paths exist,but __________ are more helpful in the hands-on task of managing the project.
A) Networks,Gantt charts
B) Activity sets,networks
C) Gantt charts,networks
D) Gantt charts,activity sets
Correct Answer:

Verified
Correct Answer:
Verified
Q19: In the AOA network,arrows depict _.<br>A)networks<br>B)events<br>C)activities<br>D)dummy activities
Q20: The shortest time in which the entire
Q21: The variance of a population is a
Q22: Describe the benefits of forming a network
Q23: In a network,if the delay of an
Q25: A(n)_ is a specific task or set
Q26: Assume that task J has a most
Q27: Task F has duration of 10 days
Q28: Slack is also known as _.<br>A)critical path<br>B)scope<br>C)float<br>D)precedence
Q29: In CPM,an activity can be conducted at