Multiple Choice
In CPM, __________ are specified.
A) exact levels of uncertainty associated with activities
B) an expected time, a crash time, and the standard deviation time
C) three costs
D) Two activity times and two costs
Correct Answer:

Verified
Correct Answer:
Verified