Multiple Choice
If deterministic time estimates are used,and if project deadlines are firm,there is a high likelihood that it will __________.
A) not be necessary to crash any activities in projects
B) be necessary to crash the last few activities of most projects
C) be completed on time and within budget
D) be completed as per schedule
Correct Answer:

Verified
Correct Answer:
Verified