Multiple Choice
The formula for computing the cost / time slope for each activity that can be crashed is __________.
A) (crash cost + normal cost) / (crash time + normal time)
B) (crash cost - normal cost) / (crash time - normal time)
C) (normal cost + crash cost) / (normal time + crash time)
D) (normal cost - crash cost) / (normal time - crash time)
Correct Answer:

Verified
Correct Answer:
Verified