Multiple Choice
Because project milestones do not occur at periodic intervals, go/no-go controls should be linked to the __________; not simply to the calendar.
A) actual plans and to the occurrence of real events
B) corporate budgeting process
C) portfolio management review process
D) capital budgeting process
Correct Answer:

Verified
Correct Answer:
Verified