Solved

Because Project Milestones Do Not Occur at Periodic Intervals, Go/no-Go

Question 26

Multiple Choice

Because project milestones do not occur at periodic intervals, go/no-go controls should be linked to the __________; not simply to the calendar.


A) actual plans and to the occurrence of real events
B) corporate budgeting process
C) portfolio management review process
D) capital budgeting process

Correct Answer: