During the Initiation Project Stage, Project Audits/evaluations Can Provide Significant

Question 43

Multiple Choice

During the initiation project stage, project audits/evaluations can provide significant value if the audit takes place early, prior to __________ completion of the initial planning stage.


A) 10 percent
B) 25 percent
C) 50 percent
D) 75 percent