Multiple Choice
During the initiation project stage, project audits/evaluations can provide significant value if the audit takes place early, prior to __________ completion of the initial planning stage.
A) 10 percent
B) 25 percent
C) 50 percent
D) 75 percent
Correct Answer:

Verified
Correct Answer:
Verified