Resourced Minerals Inc.agrees to deliver ten tons of coal to Static Energy Corporation.The agreement states that delivery is to be within "9" days, although the parties intend "90" days.Resourced Minerals cannot convince Static Energy to amend the contract.Resourced Minerals should seek


A) damages.
B) reformation.
C) rescission.
D) specific performance.

Correct Answer: