An Unfavorable Flexible-Budget Variance for Variable Costs May Be the Result

Question 60

Multiple Choice

An unfavorable flexible-budget variance for variable costs may be the result of ________.


A) using more input quantities than were budgeted
B) paying lower prices for inputs than were budgeted
C) selling output at a higher selling price than budgeted
D) selling less quantity compared to the budgeted

Correct Answer:

verifed

Verified