Standard material cost per kg of raw material is $6.50. Standard material allowed per unit is 5 Kg. Actual material used per unit is 6.00 Kg. Actual cost per kg is $6.00. What is the standard cost per output unit?
A) $30.00
B) $36.00
C) $32.50
D) $39.00