Handley Manufacturing Company has prepared the following flexible budget for August and is in the process of interpreting the variances. F denotes a favorable variance and U denotes an unfavorable variance.
Handley Manufacturing Company has prepared the following flexible budget for August and is in the process of interpreting the variances. F denotes a favorable variance and U denotes an unfavorable variance.   The most likely explanation of the above variances for Material A is that ________. A)  a lower price than expected was paid for Material A B)  higher-quality raw materials were used than were planned C)  the company used a higher-priced supplier D)  Material A used during September was $2,000 less than expected
The most likely explanation of the above variances for Material A is that ________.


A) a lower price than expected was paid for Material A
B) higher-quality raw materials were used than were planned
C) the company used a higher-priced supplier
D) Material A used during September was $2,000 less than expected

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions