For Heavy Manufacturing Company, labor-hours are 40,000 and wages $144,000 at the high point of the relevant range, and labor-hours are 24,000 and wages $96,000 at the low point of the relevant range.
What is the slope coefficient?
A) $3.75
B) $3.00
C) $3.60
D) $4.00
Correct Answer: