Multiple Choice
Ventaz Corp manufactures small windows for back yard sheds. Historically, its demand has ranged from 30 to 50 windows per day with an average of 43. Alex is the one production worker and he works eight hours a day, five days a week. Each order is one window and each window takes 7 minutes. Alex plans to add doors to its product line and anticipates that they will average 2 doors per day. Each door takes V4 minutes to install.
What is the average waiting time, in minutes, if Alex continues to be the only worker?
A) 220 minutes
B) 289 minutes
C) 241 minutes
D) 963 minutes
Correct Answer:

Verified
Correct Answer:
Verified
Q65: Distribution of questionnaires to customers regarding product
Q66: Longer manufacturing cycle times increase the inventory
Q67: Rework is an example of _.<br>A) prevention
Q68: Tran-North American Industries Inc. is looking at
Q69: Cost of Quality (COQ) reports provide more
Q71: Monticello Corp manufactures expensive tables. Its varnishing
Q72: Which of the following is a learning-and-growth
Q73: Cysco Corp has a budget of $1,210,000
Q74: Manufacturing Cycle Efficiency (MCE) = Value-added Manufacturing
Q75: Product testing is an example of _.<br>A)