Multiple Choice
The tool crib at a large manufacturing company is responsible for providing tools to the factory workers on demand. The tool crib has a variable demand. Historically, its demand has ranged from 220 to 500 small tools per day with an average of 360. Diane, the tool crib attendant, works eight hours a day, five days a week. Each order is for one small tool and each small tool takes Diane 1 minute to retrieve from the bins.
Diane has been asked to consider plans to add the retrieval of larger tooling fixtures to her duties. She anticipates that there would be an average of 10 tooling fixtures per day requested. Each tooling fixture would take Diane 4 minutes to retrieve.
What is the average waiting time, in minutes, if Diane continues to be the only worker that would retrieve the small tools as well as the larger tooling fixtures?
A) 0.50 minutes
B) 5.00 minutes
C) 3.25 minutes
D) 160.00 minutes
Correct Answer:

Verified
Correct Answer:
Verified
Q1: What are ISO 9000 and ISO 14000?
Q3: Cysco Corp has a budget of $1,200,000
Q4: The implication of controlling a process at
Q5: Zenich Corp manufactures laptops. The waiting time
Q6: An important difference between financial measures of
Q7: Which of the following is a storage
Q8: Which of the following reduces manufacturing cycle
Q9: Which of the following is true of
Q10: The two basic aspects of quality are
Q11: Which of the following is the mathematical