A "Push-Through" System, Often Described as a Materials Requirement Planning

Question 17

True/False

A "push-through" system, often described as a materials requirement planning system, focuses first on the forecasted amount and timing of finished goods and then determines the demand for materials components and subassemblies at each of the prior stages of production.

Correct Answer:

verifed

Verified