Multiple Choice
Which of the following is a stage of the capital budgeting process that forecasts all potential cash flows attributable to the alternative projects?
A) identify projects stage
B) make decisions by choosing among alternatives stage
C) implement the decision, evaluate performance, and learn stage
D) make predictions stage