Solved

In Using the Net Present Value Method, Only Projects with a Zero

Question 64

Multiple Choice

In using the net present value method, only projects with a zero or positive net present value are acceptable because ________.


A) the return from these projects equals or exceeds the cost of capital
B) a positive net present value on a particular project guarantees company profitability
C) the company will be able to pay the necessary payments on any loans secured to finance the project
D) it results in high payback period

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge