True/False
The project sponsor and project champion should be the same person on any project.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q69: Scope statements should include,at a minimum,a description
Q70: _ dependencies involve relationships between project and
Q71: Project _ involves devising and maintaining a
Q72: A(n)_ is a significant event on a
Q73: Identify and describe the four types of
Q75: Specifications on a WBS represent work that
Q76: The main groupings for the work in
Q77: Every item on a WBS needs to
Q78: How does Global Construction implement team contracts?
Q79: The project team develops a preliminary scope