Activity ____ Provide Schedule-Related Information About Each Activity,such as Predecessors,successors,logical
Multiple Choice
Activity ____ provide schedule-related information about each activity,such as predecessors,successors,logical relationships,leads and lags,resource requirements,constraints,imposed dates,and assumptions related to the activity.
A) features
B) characteristics
C) properties
D) attributes
Correct Answer:

Verified
Correct Answer:
Verified