Multiple Choice
____ development uses the results of all the preceding project time management processes to determine the start and end dates of project activities and of the entire project.
A) Task
B) Schedule
C) Work Package
D) Activity
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q10: Provide a description of project time management,including
Q11: Project _ management involves defining and controlling
Q12: _ charts provide a standard format for
Q13: In the context of a network diagram,a
Q14: _ dependencies are inherent in the nature
Q16: A(n)_ is a deliverable-oriented grouping of the
Q17: The term "_" is used to describe
Q18: You need a detailed project schedule before
Q19: A cost baseline is a(n)_ budget that
Q20: The main purpose of project planning is