Multiple Choice
____ is a technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost.
A) Crashing
B) Deflating
C) Compacting
D) Minimizing
Correct Answer:

Verified
Correct Answer:
Verified