Multiple Choice
The main disadvantage of ____ is that it can end up lengthening the project schedule,because starting some tasks too soon often increases project risk and results in rework.
A) reviewing
B) crashing
C) extending
D) fast tracking
Correct Answer:

Verified
Correct Answer:
Verified