menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management
  4. Exam
    Exam 4: Planning Projects, part I Project Integration, scope, time, and Cost Management
  5. Question
    ____ Estimates,also Called Top-Down Estimates,use the Actual Cost of a Previous,similar
Solved

____ Estimates,also Called Top-Down Estimates,use the Actual Cost of a Previous,similar

Question 48

Question 48

Multiple Choice

____ estimates,also called top-down estimates,use the actual cost of a previous,similar project as the basis for estimating the cost of the current project.


A) Homologous
B) Analogous
C) Sequential
D) Parallel

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q43: The critical path is the shortest path

Q44: Performance in meeting project scope goals is

Q45: There are _ basic reasons for creating

Q46: Project management software uses the _ format

Q47: After you determine the reason for a

Q49: Project teams rarely estimate completion dates for

Q50: The main planning tasks performed as part

Q51: To create a good WBS,you must understand

Q52: _-also called critical path analysis-is a network

Q53: What are some important questions to answer

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines