Multiple Choice
PMI defines a project ____ as an uncertainty that can have a negative or positive effect on meeting project objectives.
A) hazard
B) danger
C) risk
D) challenge
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q50: Many people should be responsible for monitoring
Q51: Project _ management includes acquiring or procuring
Q52: Under which risk register heading would you
Q53: _ contracts involve payment to the seller
Q54: Which of the following is a key
Q56: By having suppliers visibly compete against each
Q57: Under which risk register heading would you
Q58: Examples of common _ used by organizations
Q59: It is important to effectively plan the
Q60: _ to requirements means that the project's