Multiple Choice
In the context of earned value management,____ are calculated by subtracting the actual cost or planned value from EV,and indexes are calculated by dividing EV by the actual cost or planned value.
A) fluctuations
B) valuations
C) variances
D) deviations
Correct Answer:

Verified
Correct Answer:
Verified