Multiple Choice
What is the critical path in a PERT/CPM diagram?
A) The chain of activities that takes the longest time to proceed through the network
B) The chain of activities that contains the greatest amount of slack
C) The chain of activities that contains the largest number of nodes
D) The chain of activities with the earliest finish time
E) The chain of activities with the fewest nodes
Correct Answer: