Which of the Following Methods for Setting Production Standards Is

Question 44

Multiple Choice

Which of the following methods for setting production standards is most likely to be used for noncyclical types of work in which many different tasks are performed and there is no set pattern or cycle?


A) Expert opinion
B) Work sampling
C) Performance of specially selected employees
D) Time study
E) Average production

Correct Answer:

verifed

Verified

Unlock this answer now