Multiple Choice
A(n) _________,which is a project management technique,can be established using the critical path to list the completion time of a project on the x-axis and all the activities on the y-axis.
A) work breakdown structure
B) event chain diagram
C) Gantt chart
D) risk register
Correct Answer:

Verified
Correct Answer:
Verified