Multiple Choice
The first step in applying PERT is to
A) estimate the time required for each activity and mark it on the corresponding arrow.
B) identify all of the major activities involved in the project.
C) arrange the events in a sequence.
D) use arrows, representing activities, to connect events that must occur in sequence.
E) identify the critical path.