Multiple Choice
When requesting vendor bids,the project management team prepares a__________ ,a document specifying all the system requirements and soliciting a formal plan from each vendor contacted.
A) request for comments (RFC)
B) request for quotation (RFQ)
C) request for proposal (RFP)
D) request for information (RFI)
Correct Answer:

Verified
Correct Answer:
Verified