Solved

The Process Design Team at a Manufacturer Has Broken an Assembly

Question 14

Multiple Choice

The process design team at a manufacturer has broken an assembly process into eight basic steps,each with a required time,and predecessor as shown in the table.There are 7.5 productive hours available in a day and the manufacturer wishes to produce 400 units.Balance the line by assigning tasks to workstations to fill up as much takt time as possible.Break ties by assigning the longest task first.What task(s) should be assigned at the third workstation? The process design team at a manufacturer has broken an assembly process into eight basic steps,each with a required time,and predecessor as shown in the table.There are 7.5 productive hours available in a day and the manufacturer wishes to produce 400 units.Balance the line by assigning tasks to workstations to fill up as much takt time as possible.Break ties by assigning the longest task first.What task(s) should be assigned at the third workstation?   A) B and E B) D C) C,E,and G D) F


A) B and E
B) D
C) C,E,and G
D) F

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions