Multiple Choice
A hatmaker,fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year.He and his space designer have identified seven activities that are necessary to expand his small shop.For the sake of simplicity,and to avoid giving away any trade secrets,the activities have been identified by letters A-G.The activities,their time estimates,and the precedence requirements structure are listed in the table immediately below.
-Which of the activities in this project has the greatest amount of slack?
A) B
B) C
C) D
D) E
Correct Answer:

Verified
Correct Answer:
Verified
Q20: In the project definition phase, project planners
Q29: A critical path is composed entirely of
Q35: The BEST use of a Gantt chart
Q37: The longest path in a network from
Q39: Key points in a project,such as when
Q40: A(n)_ is a graphical tool that should
Q41: Program evaluation and review technique, PERT, is
Q43: Given the early and late finish times
Q44: One of the primary characteristics of projects
Q63: The actual work gets done during the