Solved

The Project Represented by This Network Diagram Has Activity Lengths

Question 53

Multiple Choice

The project represented by this network diagram has activity lengths in days and crash costs as shown in the table.
The project represented by this network diagram has activity lengths in days and crash costs as shown in the table.      -What is the cheapest completion cost for the project if the contractor must complete all work in 45 days? A) $550 B) $950 C) $1150 D) $1450 The project represented by this network diagram has activity lengths in days and crash costs as shown in the table.      -What is the cheapest completion cost for the project if the contractor must complete all work in 45 days? A) $550 B) $950 C) $1150 D) $1450
-What is the cheapest completion cost for the project if the contractor must complete all work in 45 days?


A) $550
B) $950
C) $1150
D) $1450

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions