Solved

The Project Represented by This Network Diagram Has Activity Lengths

Question 44

Multiple Choice

The project represented by this network diagram has activity lengths in days and crash costs as shown in the table.The fixed cost for being on site is $450.What is the lowest total completion cost for the project? The project represented by this network diagram has activity lengths in days and crash costs as shown in the table.The fixed cost for being on site is $450.What is the lowest total completion cost for the project?     A) $10,600 B) $11,000 C) $11,400 D) $12,000 The project represented by this network diagram has activity lengths in days and crash costs as shown in the table.The fixed cost for being on site is $450.What is the lowest total completion cost for the project?     A) $10,600 B) $11,000 C) $11,400 D) $12,000


A) $10,600
B) $11,000
C) $11,400
D) $12,000